Three-phase
unit versus single-phase units:
Since the
transmission system is 3-phase, transformers may be built as 3-phase single
units or as three single-phase units into delta and star combinations or
groups.
Advantages
of 3 phase units
- They
occupy less space
- No
extra support equipment is required to form a 3-phase Delta or Star
connection.
- They
are cheaper
- They
can be transported from factory as a compact unit, erected and
commissioned
at site quickly
- Compact
on-load tap changing (OLTC) gear can be provided as a built in unit.
Disadvantages
of 3 phase units
·
Problem
of transportation in case of large capacity units weighing more than 100 tons.
·
Takes
time in assembling, erecting and commissioning if parts are dismantled and sent
to site.
·
The
cost of one spare 3-phase transformer is more.
·
Change
of connections from star to delta or vice-versa cannot be done.
·
If
reconditioning is undertaken then the complete unit has to be taken out of
service and this becomes a problem if no spare capacity is available.
Advantages
of Single-Phase Units
- The
cost of a spare transformer is the cost of a single-phase unit, which is
comparatively very much less than the cost of a complete spare 3-phase
unit.
- They
can be transported to site as completely assembled units and commissioned
quickly.
- Reconditioning
can be undertaken on individual units with a minimum outage time.
- It is
possible to obtain different possible pairs of connections between the
primary and secondary.
Disadvantages
of Single-Phase Units
- They
occupy more space
- They
require additional support structure to form 3-phase connections.
- Expenditure
on civil engineering works is more
- The
problem of providing on-load tap changing gear and even if provided the
cost of providing tap changing gear on each unit works out costlier by at
least 50% when compared to a compact unit in a 3-phase transformer.
Considering all the above, there is little argument in
favour of the adoption of single-phase units as compared to 3-phase units. Single-phase units are the only choice where
3-phase units cannot be transported because of their weight and dimensions and
also if there are no facilities at site for the assembly, preparation and
commissioning of the 3-phase unit
Power
Transformers
These are transformers of high rating
of generally not less than 5MVA and 33KV and the rating also increases with the
voltage rating. They may be of the step-up type installed at generating
stations or of the step-down type installed at substations. They have a high
utilisation factor, which means that they are arranged to work at a constant
load equal to their rating. Hence their
maximum efficiency is designed to be at or near full load. Such power transformers installed in
substations are provided with OLTC gear to regulate the voltage to be within
permissible limits during peak load and off peak load hours.
However, generator step-up power
transformers are provided with only off circuit taps.
Distribution
Transformers
These are transformers installed in
H.V. distribution feeders to meet consumer voltage requirements. These are generally rated at 11KV and have a
rating not exceeding 1000KVA. These
transformers are characterised by an intermittent variable load, which is
usually considerably less than the full load rating. They are therefore designed to have their
maximum efficiency at between half and three quarter of full load. These transformers are not provided with any
OLTC gear but with only off circuit taps.
Auto Transformers
An Auto Transformer is a transformer
with a common winding for both primary and secondary. They are used in place of
two winding power transformers where the ratio of transformation does not
exceed 2 as they are cheaper than two winding transformers such as in a
132KV/66KV system or 66KV/33KV system.