Transformer Test
Transformer test are done to
determine the electrical, thermal and mechanical suitability for the system
where they will be applied or use. The major tests carried out in the
transformers are:
Turn ratio test(open
circuit test)
The
performance of a transformer largely depends upon perfection of specific turns
or voltage ratio of transformer. So transformer ratio test is an essential type test of transformer. This test also performed as routine
test of transformer. So for ensuring proper performance of
electrical power transformer, voltage and turn ratio test of transformer is one
of the vital tests.
This
is also used to make sure that the turn ratio between the windings of the
transformers is correct; with this information, you can decide what the output
voltage of the transformer will be. The ratio is calculated under no load
condition.
Simultaneous
readings of voltage are taken to high voltage and low voltage windings area
taken after the voltage is applied on one winding and on each taps if the
transformer has a tap changer. The ratio is the division between the high
reading and low reading. If it is a three phase transformer each phase is
tested individually. Expected variation should be between 0.5%.
Procedures: The instrument use to test is
multimeter. Assume the transformer we are testing is a 60MVA/132/33kv
transformer with 10 taps. First of all note the nominal tap of the transformer
before you proceed (but normally written on the name plate of the transformer)
then a supply voltage of 415volt is connected at the primary side of the
transformer 132kv while the secondary side of the transformer is open
circuited, then with your multimeter take the line voltage of both the primary
and secondary side of the transformer i.e. R-Y, R-B, B-Y .This is done in all
the taps 1-10
Insulation
resistance test
Insulation
resistance test of transformer
is essential type test, it is commonly known as megger test. This test is
carried out to ensure the healthiness of overall insulation system of an electrical
power transformer. It measures the quality of insulation within the
transformer. Some variation will be obtainable depending on the moisture,
cleanliness and the temperature of the winding. It is recommended that core and
tank should always be grounded when the test is performed. Each winding should
be short circuited at the bushing terminals. Resistances are measured between each winding and all other
winding to ground.
Procedure of Insulation Resistance test of transformer
1)
First disconnect all the line and neutral terminals of the transformer.
2) Megger leads to be connected to LV and HV bushing studs to measure Insulation Resistance IR value in between the LV and HV windings.
3) Megger leads to be connected to HV bushing studs and transformer tank earth point to measure Insulation Resistance IR value in between the HV windings and earth.
4) Megger leads to be connected to LV bushing studs and transformer tank earth point to measure Insulation Resistance IR value in between the LV windings and earth.
2) Megger leads to be connected to LV and HV bushing studs to measure Insulation Resistance IR value in between the LV and HV windings.
3) Megger leads to be connected to HV bushing studs and transformer tank earth point to measure Insulation Resistance IR value in between the HV windings and earth.
4) Megger leads to be connected to LV bushing studs and transformer tank earth point to measure Insulation Resistance IR value in between the LV windings and earth.
NB
: It is unnecessary to perform insulation
resistance test of transformer per phase wise in three phase
transformer. IR values are taken between the windings collectively as because
all the windings on HV side are internally connected together to form either
star or delta and also all the windings on LV side are internally connected
together to form either star or delta.
Measurements
are to be taken as follows:
For Auto Transformer: HV-IV to LV, HV-IV to E, LV to E
For Two Winding Transformer: HV to LV, HV to E, LV to E
Three Winding Transformer: HV to IV, HV to LV, IV to LV, HV to E, IV to E, LV to E
Oil temperature should be noted at the time of insulation resistance test of transformer. Since the IR value of transformer insulating oil may vary with temperature.
For Auto Transformer: HV-IV to LV, HV-IV to E, LV to E
For Two Winding Transformer: HV to LV, HV to E, LV to E
Three Winding Transformer: HV to IV, HV to LV, IV to LV, HV to E, IV to E, LV to E
Oil temperature should be noted at the time of insulation resistance test of transformer. Since the IR value of transformer insulating oil may vary with temperature.
Short
circuit test
This
test is done to determine the impedance voltage which gives an idea of how much
load the transformer can carry.
Procedures: The instrument use to test is
multimeter. Assume the transformer we are testing is a 60MVA/132/33kv
transformer with 10 taps. First of all note the nominal tap of the transformer
before you proceed (but normally written on the name plate of the transformer)
then a supply voltage of 415volt is connected at the primary side of the
transformer 132kv while the secondary side of the transformer is short
circuited, then with your multimeter take the line voltage of both the primary
and secondary side of the transformer i.e. R-Y, R-B, B-Y .This is done in all
the taps 1-10
Magnetizing Current
Test
Magnetizing current test of
transformer is
performed to locate defects in the magnetic core structure, shifting of
windings, failure in turn to turn insulation or problem in tap changers. These
conditions change the effective reluctance of the magnetic circuit, thus
affecting the electric current required to establish flux in the core.
1)
First of all keep the tap changer in the lowest position and open all IV &
LV terminals.
2) Then apply three phase 415V supply on the line terminals for three phase transformers and single phase 230V supply on single phase transformers.
3) Measure the supply voltage and electric current in each phase.
4) Now repeat the magnetizing current test of transformer test with keeping tap changer in normal position.
5) And repeat the test with keeping the tap at highest position.
2) Then apply three phase 415V supply on the line terminals for three phase transformers and single phase 230V supply on single phase transformers.
3) Measure the supply voltage and electric current in each phase.
4) Now repeat the magnetizing current test of transformer test with keeping tap changer in normal position.
5) And repeat the test with keeping the tap at highest position.
Generally
there are two similar higher readings on two outer limb phases on transformer
core and one lower reading on the centre limb phase, in case of three phase
transformers. An agreement to within 30 % of the measured exciting current with
the previous test is usually considered satisfactory. If the measured exciting
current value is 50 times higher than the value measured during factory test,
there is likelihood of a fault in the winding which needs further analysis.
No comments:
Post a Comment